1: When installing or replacing new or old molds, be sure to avoid collisions and bumps, assemble in a civilized manner, and pay attention to the maintenance of the molds;
2: During use, check the mold size and the condition of the welding joints frequently. If there are cracks in the welds, they should be repaired in time. If there is excessive wear, the aggregate particle size should be adjusted. If excessive wear affects the quality of the product, a new mold should be purchased;
3: Carefully adjust the gap, including the spacing between the pressure head and the mold core, the pressure head and the moving plane of the material car, the mold frame and the wire plate, etc. Relative movement must not interfere or rub;
4: When cleaning the mold daily, use an air compressor and soft tools to remove concrete residues. It is strictly forbidden to knock or pry the mold with gravity;
5: The replaced mold should be cleaned, oiled to prevent rust, and placed flat on a dry and flat place to prevent gravity deformation.
6: Cleaning. We think that many bulky equipment are very troublesome to clean. It is also because of the bulkiness that we think that the equipment hardly needs to be cleaned, which is wrong. Whether the equipment needs to be cleaned depends on the working conditions. We humans need to take a shower every day when working in a very dirty environment. The same is true for equipment. The mold, pump station, and distribution cabinet must be cleaned every day after the cement brick machine is completed.
7: Before production every day, please check all parts of the cement brick machine, such as the tightness of the screws, the tightness of the motor belt, the joints of the welding gaps, and other details.